Trent Gateway
Discover Upperton’s cutting-edge Nottingham facility
After operating for over 24 years, we are expanding our expertise in the UK, Trent Gateway is Upperton’s newest facility offering a tenfold increase in our drug development and manufacturing capacity.
This new state-of-the-art Nottingham site brings 10 new GMP manufacturing suites, quality control laboratories and dedicated analytical and formulation development laboratories with pilot plant facilities. With greater capabilities and the latest technological advancements, Trent Gateway offers faster turnaround times, increased efficiency and greater flexibility to accommodate your ever-evolving pharmaceutical needs.
Trent Gateway has been specifically designed to cater to a wide range of development and manufacturing projects, offering processing of non-sterile dosage forms including solids, liquids, semi-solids, nasal and inhaled products.
Whether you’re in the early stages of formulation development, in need of clinical trial supplies from Phase 1 to Phase 3 or seeking niche-scale commercial manufacturing, Trent Gateway is fully equipped to fulfil your requirements with precision and excellence.
Trent Gateway in numbers
GMP Manufacturing footprint
increased to
12,000 sqft
Analytical footprint
increase to
8,000 sqft
10 contained GMP manufacturing rooms up to 700 sqft
From concept to build in 10 months
Business decision to expand
October2021
New site location found
November2021
First trip for staff to new site
December2021
Site design Stage 2 completed
March 2022
Inflexion Investment completed
April2022
Building Lease signed and got the keys!
May2022
Stage 3 design completed
October 2022
Site build commenced
December2023
Site build and Design Qualification completed
June2023
Gerteis Roller Compactor delivery
July2023
Facility commissioning to be initiated
August2023
Offices open
August2023
Tabletting and Coating equipment delivery
September2023
Capsule machine delivery
October2023
QC lab opens
November2023
GMP facility open for non-GMP activities
November2023
Previous
Next
October 2021
Decision to expand
New site identified
QC Labs Open
October 2023
QC Labs Open
October 2023
QC Labs Open
October 2023